Salem Council Votes 6-2 to Exclude Large AI Data Centers Under Existing Zoning Code

The decision could affect Verrus' pending Oakline at Mill Creek proposal as the city prepares a separate hearing on future development rules.

Salem Council Votes 6-2 to Exclude Large AI Data Centers Under Existing Zoning Code
Key Takeaways
The Main Point

Salem City Council voted 6-2 on November 17, 2026, to adopt Resolution No. 2026-46, interpreting the city's existing zoning code as excluding certain large AI and hyperscale data centers.

What the Decision Means

The council determined that facilities primarily dedicated to large-scale computational processing do not fall under the existing "data center facilities" classification in Salem Revised Code Section 400.110(e). The decision does not prohibit every type of data center.

Why Businesses Care

The interpretation could affect Verrus' pending Oakline at Mill Creek development proposal. Supporters argued that modern AI facilities differ from traditional data centers, while opponents warned that revisiting zoning interpretations could create uncertainty for developers and investors.

What Comes Next

A public hearing on proposed data center code amendments is scheduled for November 23, with a second reading tentatively planned for December 7. The Data Center Task Force is also expected to present recommendations in December. The November 17 interpretation could face a legal appeal.

FAQs (Click here)
Did Salem ban all data centers?

No. The council adopted an interpretation of the existing zoning code that excludes facilities whose principal defining function is large-scale computational processing, such as certain AI and hyperscale data centers. Traditional data centers are not categorically excluded by this interpretation.

Was the Verrus data center project rejected?

No. The November 17 vote was not a decision to approve or deny Verrus' Oakline at Mill Creek application. However, the interpretation could affect how the proposed development is evaluated under existing land-use regulations.

Who voted for and against the resolution?

Councilors Paul Tigan, Linda Nishioka, Irvin Brown, Mai Vang, Vanessa Nordyke and Micki Varney voted in favor. Mayor Julie Hoy and Councilor Deanna Gwyn voted against it. Councilor Shane Matthews was absent.

Can the city's decision be challenged?

Yes. City Attorney Dan Atchison acknowledged that an appeal to Oregon's Land Use Board of Appeals (LUBA) is possible. The board could uphold the interpretation, return it for further proceedings or reverse it, depending on its findings.

When can the public weigh in on future data center regulations?

Salem City Council has scheduled a public hearing for November 23, 2026, to consider proposed amendments addressing data center development. Those amendments are separate from the November 17 interpretation and could establish updated standards for future projects. Residents and businesses can follow meeting details through the City of Salem website.

Salem City Council voted 6-2 Tuesday, Nov. 17, to interpret its zoning code as excluding certain large AI and hyperscale data centers, a decision that could alter the path for a major development proposal in southeast Salem.

The adopted Resolution No. 2026-46 addresses Salem Revised Code Section 400.110(e), which defines "data center facilities." Council members concluded that the existing category, based on characteristics established in 2013 and 2014, does not cover operations whose principal defining function is large-scale computational processing.

That distinction matters for Verrus, whose subsidiary Alderstone LLC has filed an application for Oakline at Mill Creek at 4720 Mill Creek Drive SE. The city's land-use portal describes two one-story buildings totaling 600,000 square feet. The application remains listed as "Application Received." Tuesday's vote was not a permit denial or approval.

City Attorney Dan Atchison said the code describes facilities principally devoted to storing and transmitting data. He acknowledged that conventional data centers also process information but argued that the intensity and primary purpose of AI computing make those facilities a different land use.

Atchison said the council's interpretation would guide city staff, although decision-makers reviewing individual land-use applications would have to reach their own conclusions.

Councilor Deanna Gwyn opposed the resolution, saying the applicant spent months working with city staff and received assurances that the use was permitted. She warned that revisiting the meaning of existing regulations during an application could undermine business confidence.

"I also believe Salem has to be a place where the rules mean what they say, no matter how unpopular an applicant is," Gwyn said.

Mayor Julie Hoy also voted no, questioning whether the existing code supports the distinction the council was adopting.

Councilors Micki Varney and Vanessa Nordyke argued that rapidly changing technology and demands on infrastructure warranted a closer reading of the older code. Councilor Paul Tigan said the interpretation was reasonable despite legitimate disagreement over its meaning.

Tigan, Linda Nishioka, Irvin Brown, Mai Vang, Nordyke and Varney voted in favor. Gwyn and Hoy opposed it. Councilor Shane Matthews was absent.

The decision followed a Nov. 9 public hearing and thousands of pages of written testimony. Deliberations were postponed after a Microsoft Outlook outage disrupted submissions on Nov. 12. The rescheduled meeting was held virtually because Loucks Auditorium at Salem Public Library was unavailable.

Atchison acknowledged that the decision could be appealed to Oregon's Land Use Board of Appeals. He argued that the interpretation was legally plausible but did not guarantee it would survive a challenge.

The city plans a separate public hearing Nov. 23 on proposed amendments establishing future rules for data centers and battery energy storage systems. A second reading is tentatively scheduled for Dec. 7, and the city's Data Center Task Force is expected to deliver recommendations in December.

Those steps remain separate from Tuesday's interpretation.