Salem City Council voted 7-2 Monday to replace a proposed 10-megawatt electricity cap on future data centers with a 60,000-square-foot building size limit, changing how the city intends to regulate an industry facing growing scrutiny over its demands on local infrastructure.
If adopted, the restriction would make it considerably more difficult for large-scale data center developers to establish operations in Salem. Verrus, the company behind the proposed Oakline at Mill Creek development in southeast Salem, submitted plans for two buildings totaling 600,000 square feet, 10 times the proposed size limit.
The Verrus development could not proceed as currently designed if subjected to the new standards. However, because the company submitted its application July 31, Oregon land-use law generally requires qualifying applications to be evaluated under the regulations in place when they were first submitted.
The more immediate obstacle for Verrus is the council’s Nov. 17 decision interpreting existing zoning regulations as excluding certain AI and hyperscale data centers. That interpretation could face a legal challenge.
For companies such as Google, OpenAI and other major technology developers, the proposed size restriction would substantially limit opportunities to build large-scale computing campuses in Salem. Smaller facilities could still be permitted, provided they meet the city’s zoning, environmental and infrastructure requirements.
The decision followed testimony from Portland General Electric, Salem Electric and NW Natural, which urged the city to regulate data centers through traditional land-use standards rather than restrictions on electricity consumption.
Councilor Paul Tigan introduced the alternative, arguing that regulating building size would put Salem on stronger legal footing while maintaining restrictions on large-scale development.
Tigan expressed concern that a successful legal challenge to an electricity cap could leave Salem without adequate protections once its temporary data center moratorium expires.
City planner Bryce Bishop explained that a 60,000-square-foot facility could consume between five and 12 megawatts based on general industry estimates. However, advances in technology could allow future facilities to consume considerably more electricity within the same footprint.
That distinction leaves open the possibility of developers operating increasingly powerful computing facilities in Salem without exceeding the proposed building size restriction. How the limit would apply to developments consisting of multiple buildings will also depend on the final ordinance language.
Councilors Mai Vang and Micki Varney opposed the amendment.
Representatives from the three utilities argued that electricity consumption alone does not determine a facility’s water use, noise levels or effects on neighboring properties. They maintained that utility providers are better positioned to evaluate electrical capacity and service requirements.
Residents who supported the original 10-megawatt cap raised concerns about electricity affordability, water availability, environmental impacts and neighborhood livability.
The council also voted 6-3 to prohibit diesel backup generators at data centers subject to the proposed additional development standards. A separate amendment requiring facilities to obtain a majority of their electricity from qualifying renewable sources passed by the same margin.
Other proposed regulations include restrictions on where data centers may operate, additional noise monitoring, water-efficient cooling systems and requirements demonstrating that public infrastructure can accommodate new facilities.
Residential battery energy storage systems would be exempt from additional requirements intended for industrial-scale installations.
Unlike the Nov. 17 zoning interpretation, the new ordinance would establish updated development standards rather than interpret regulations adopted more than a decade ago.
Councilors unanimously advanced Ordinance Bill No. 17-26 to second reading. Several emphasized that their support for individual amendments did not necessarily represent approval of the final language.
The proposed regulations are intended as an interim measure while Salem’s Data Center Task Force completes its recommendations and state officials consider broader data center policies.
City staff are expected to return Dec. 14 with revised ordinance language. The council also unanimously agreed to revisit the regulations no later than Oct. 1, 2027.